Projects
Defining a Factory Roadmap
Context
On their roadside assistance vehicle equipment business, Our client is lagging behind in terms of industry best practices. A thorough diagnosis of their operations must help identify strategic performance improvement areas, and ultimately enable the doubling of their productivity.
Diagnosis
Evaluating the industrial maturity of the factory
—
A 5-axis diagnosis was performed to evaluate the company’s maturity in the following domains:
Automation
Industrie 4.0
Layout & Footprint
Operational Excellence
Organizational structure
This diagnosis consisted of several steps :
Plant visit to observe real-time operations
Interviews with employees of all hierarchical levels
Workshops with relevant stakeholders (including VSM : Value Stream Mapping)
Analysis of relevant available data (including operation times)
Our Solutions
Following the diagnosis, a total of 17 actions were identified to boost the factory’s performance. 3 out of these 17 actions were qualified as essential, as their potential impact relative to their costs of implementation (in terms of investment and change management) were the most promising.
A general transformation roadmap was produced, and several workshops were conducted to refine the target and intermediate stages on the 3 most promising actions for performance improvement. The refining process involved both Dillygence’s Lean expertise, and the operational expertise of client’s project leaders and key stakeholders on these particular issues.
Benefits
A general transformation roadmap was produced, and several workshops wereconducted to refine the target and intermediate stages on the 3 most promisingactions for performance improvement. The refining process involved both Dillygence’sLean expertise, and the operational expertise of client’s project leaders and keystakeholders on these particular issues.Solution implementation
Conducting change to reach targets
—
A 1-year schedule was designed to quickly implement the solutions designed in earlier stages and build a lasting impact on the factory. Dillygence was responsible for continuously supporting and monitoring the effort, and ensure the momentum of the design phase was not lost.